November 13, 2026-Fort Snelling, Minnesota, USA: A Metro Transit Blue Line train stops at Terminal 1 station. (H. Jiahong Pan for Hennepin Herald)
Hennepin County and the Metropolitan Council were expected to reach an agreement to plug a $224 million gap to build the Blue Line extension by Halloween. Plugging the gap would allow the two entities to apply for $752 million in federal funds needed to build the project.
Halloween came and went. The gaping hole still remains.
The lapse in the deal, plus changes by the federal government to prioritize distributing transportation project dollars to areas with higher birth and marriage rates, may make it hard for the county and the Met Council to secure funds to build the controversial Blue Line extension.
Project planners say they are not able to seek a higher grant amount from the federal government to build the project. Federal law allows agencies to pursue up to 80 percent of funding to build a new or extend an existing light rail project, so long as it is supported by an “acceptable” amount of local funds. Though Hennepin County and the Met Council are seeking a 22 percent share and have local funding committed, Hennepin County Public Works Director Lisa Cerney said, at an August county board meeting, that negotiating with the federal government for an increased appropriation “was not a viable option.”
Transportation researcher Yonah Freemark found that the Federal Transit Administration has been reluctant to fund transit projects at all. They have been slow to issue capital grants for similar projects across the nation. And, they are considering prioritizing projects for funding based on “cost effectiveness,” with projects along corridors with higher-than-average birth and legal marriage rates receiving bonus points. The U.S. Census estimates 47.8 percent of the population aged 15 and up are now legally married; tracts within one mile of the project corridor have an average legal marriage rate of only 36.8 percent.
In other words, projects like these might not necessarily be the Trump administration’s favorite hole to plug, because of the Blue Line extension corridor’s lower-than-national average marriage rate.

Map of marriage rates of people 15 and up in Census tracts within a 1-mile buffer of the proposed Blue Line extension. (Source: U.S. Census ACS 2024 5-Year Estimates, Metropolitan Council.) (Map by H. Jiahong Pan for Hennepin Herald)
How was the gap created in the first place?
In 2024, Hennepin County and the Met Council estimated the project would cost $3.2 billion to build. In June of this year, planners estimated it would cost $3.58 billion to build. Planners say the three major reasons for the cost increase was the need to add a station at Washington and West Broadway, at the request of the city of Minneapolis as a condition of approval through a state-mandated process; redesign of the Lowry Avenue station to ensure tracks did not intersect directly with the parkway; and to build new streets in North Loop so planners could convert 10th Avenue North between Washington and North 5th Street into a bike, walk, and light rail-only street. About 32 percent of the project budget is set aside to account for “ongoing economic volatility and uncertainty,” according to the Met Council.
To fill the gap, they’ve reconfigured the project and ended up saving $190 million, bringing the project costs down to $3.39 billion. Part of that came from having a better understanding of what they needed to build out the project, which saves $80 million.
In August, the Met Council opted to build a surface parking lot and operator restroom instead of structured parking at the future Oak Grove station, located on a field to the west of Target’s northern campus. This saves both Hennepin County and the Met Council $15.5 million.
Met Council and Hennepin County planners also eliminated a bridge connecting the 63rd Avenue station in Brooklyn Park to an adjacent park and ride. Doing so saves $19.1 million.
They also eliminated $75 million in finance charges, because they can use local funding sources to build the project instead of borrowing. Hennepin County commissioners in August approved committing $2.2 billion from transportation sales tax proceeds to fund the project.
Funding source | Item cut | Amount (millions) | Total funding gap (millions) | |
|---|---|---|---|---|
Hennepin additional | $1,896 | Current project budget | $3,580 | |
Anticipated FTA New Starts funding | $752 | 90% design savings | -$80 | |
Other federal | $18 | Eliminated finance costs | -$75 | |
Counties Transportation Improvement Board | $83 | Project changes in Brooklyn Park | -$35 | |
State of Minnesota | $41 | |||
Other | $13 | |||
Met Council for startup operations | $5 | |||
$358 | ||||
Total | $3,166 | Total | $3,390 | $224 |
Source: Hennepin County, Metropolitan Council |
That leaves them with $224 million remaining to fill. The Met Council isn’t able to use revenue from motor vehicle sales tax or regional transit sales tax funds to build the Blue Line extension because state law only allows the Met Council to use funds explicitly appropriated by statute or federal sources.
Talk of building a light rail line connecting the northwest suburbs dates back to the 1980s, with a formal study commenced by the Hennepin County Regional Railroad Authority in 2008. In the last decade, both Hennepin County and the Met Council decided on a route along the Burlington Northern Santa Fe (BNSF) line’s Monticello subdivision through Theodore Wirth Park and to the west of Bottineau Boulevard. The route continued due north on West Broadway in Brooklyn Park to a field across from Target’s north campus, just north of Highway 610, that is being eyed by the city of Brooklyn Park as a biotech district.
That alignment would have cost $1.5 billion to build and received a medium-high project ranking from the federal government. With that project configuration, we would likely be on a Blue Line extension train by now.
But BNSF refused to negotiate access to their right-of-way. So in 2023, planners finalized a revised route which would serve North Minneapolis along Washington and West Broadway, before continuing on the center of Bottineau Boulevard through Robbinsdale and Crystal, then joining the original alignment on West Broadway in Brooklyn Park up to the same field. This iteration of the Blue Line extension has not yet been ranked by the Federal Transit Administration.
Extension funding alternative proposals
On Nov 12, Hennepin County Commissioner Marion Greene floated a memorandum, distributed to the Blue Line extension corridor management committee members, with several funding gap proposals. These proposals were not discussed at the meeting because they were not on the agenda. Greene herself was not at the meeting, as she was participating at Hennepin Healthcare’s annual meeting in downtown Minneapolis.
The Met Council could buy 20 of the cars it needs for the Blue Line extension service using project money. The Met Council would then come up with separate funds to buy the 15 or so spare cars needed to account for the future fleet’s maintenance needs, and maybe replace some of the first-generation cars that they have, the oldest of which are 23 years old and are being sent to Louisiana for rust mitigation to extend their useful service life from the federally-mandated 31 years to 40.
The Met Council previously stated that buying spare train cars using separate funds was not feasible because they don’t have the funds budgeted elsewhere, and the legislative auditor suggested that such a move would make it harder for people to hold the agencies accountable for any changes to project costs.
Greene also suggested raiding the $598 million in funds set aside by the Met Council to operate the now-defunct Northstar rail line. Neither Hennepin County nor Met Council officials commented directly on either resolution.
Officials expect to begin construction next year, with the extension open for service in 2033. But because both Hennepin County and the Met Council have not reached an agreement to plug the funding gap to apply for federal funding, and because of federal hostility towards transit, we don’t know if the project will be ready by then.
Updates from Corridor Management Committee
The Blue Line extension Corridor Management Committee met on November 12, at Metro Transit headquarters to discuss anti-displacement funding and project updates, as well as station design. For 2027, the committee will meet four times, on February 11, June 10, September 9, and December 9. They will schedule interim meetings as needed.
The project is mostly ready to build (absent funding issues, of course). With the project 100 percent designed, Hennepin County and the Met Council are preparing to put the project out to bid next year. The stations will look similar to those on the Green Line extension, with three canopies, station marker panels that help riders identify where they are, and visual, tactile, and auditory accessibility features. The stations will not have turnstiles. Colors for the station platforms will be decided once the cultural placekeeping themes for each station are finalized, as each station will have its own theme reflecting the surrounding neighborhood.
Third-party agreements. Hennepin County and the Met Council have completed third-party agreements with Xcel Energy and BNSF, to allow for Blue Line extension construction. The Xcel agreement involves relocating transmission lines in Brooklyn Park, while the BNSF agreement allows the entities easements for grading on railroad property. Canadian Pacific Kansas City is currently entertaining an agreement with both agencies to build and maintain a third bridge above their right-of-way in Crystal.
Discord in the Anti-Displacement Community Prosperity Board. The committee has disbursed $800,000 of anti-displacement funds to local organizations through October 30 of this year. The board was established by state law in 2024, to ensure that those who live or do business along the proposed Blue Line extension remain viable before, during, and after construction. They are currently developing community agreements and a code of conduct to manage discord, to be discussed at their December meeting. Their next meetings are on November 20, from 10:00 am to 12:00 pm, and on December 3, from 1:00 to 3:00 pm. Both meetings will be at the University of Minnesota Center for Urban and Regional Affairs, 2001 Plymouth Ave. N, Minneapolis.